New approved projects (as of December 2005)

A total of 35 new projects amounting to some P87.3 million have been approved by the end of November 2005. The projects were deliberated and approved by the Executive Director, the Program Committee and the Board of Trustees.

Below is the summary of the approved projects:

Approved DSF Projects (subject to conditions stated in the screening form)

Proponent
Project Title
Project  site(s)
Project Duration
Beneficiaries
Amount Approved
Total
Ins Support Grant
Client Devt Grant
Direct Project Cost
Restricted
Grant
Loan
Grant
1
Lanas Multi-Purpose Cooperative San Jose Water System Rehab and Rainwater Harvesting Brgy Poblacion, Lendero and Combot, San Jose, Romblon 1 year 523 HHs (3138 ind)
1,788,440
24,000
42,000
1,722,440
-
-
2
Sta. Fe Multi-Purpose Cooperative Sta. Fe Water Supply Project Sta. Fe, Romblon 1 year 1000 HS students, 50 HHs (300 ind) and 163 HHs (815 innd)
193,506
24,000
42,000
127,506
-
-
3
St. Joseph Multi-Purpose Cooperative Empowering the BAWASA's to Sustain Existing Systems Looc Lone Dist., Romblon 1 year 635 HHs (3810 ind)
422,150
65,000
183,600
173,550
-
-
4
Malibago BAWASA Multi-Purpose Cooperative Rehab of Brgy Malibago Potable Waterworks System Torrijos Marinduque 1 year 479 HHs (2478 ind)
1,872,107
87,000
45,000
1,740,107
-
-
5
Sta. Cruz Credit Cooperative Imrpovement of Waterworks System for Brgy Biga Brgy Biga, Sta. Cruz Marinduque 1 year 373 individuals (88 HHs)
545,327
45,000
45,000
455,327
-
-
6
Junior Chamber International Phils - Copper Queen Presidents Assoc Inc Improvement of Waterworks System - Maniwaya Island Brgy Maniwaya, Sta. Cruz, Marinduque 1 year 1413 fisherfolks (776 female, 647 males); 194 micro- entrepreneurs (105 women)
1,103,065
45,000
45,000
1,013,065
-
-
7
Philippine Rural Reconstruction Movement (PRRM) Tungib-Lipata Water Supply System Brgy Tungib-Lipata, Buenavista Marinduque 1 year 368 HHs (1848 ind)
979,791.75
75,000
45,000
859,791.75
-
-
8
Torrijos Municipal Employees Association Matuya-Tuya-Suha Water System Torrijos Marinduque 1 year 507 HHs (2813 ind)
1,907,294
87,000
45,000
1,775,294
-
-
9
Marinducare Foundation, Inc. Construction/ Improvement of Potable Water System Brgys Boi and Bayuti; Boac, Marinduque 1 year 120 HHs (600 ind) + 23 HHs (235 ind)
1,095,844
75,000
45,000
975,844
-
-
10
Mogpog Municipal Officilas and Employees MPC Construction of Potable Water Works System Brgys Silangan, Mogpog, Marinduque 1 year 160 HHs (958 ind)
849,413
75,000
45,000
729,412.80
-
-
11
Nagkahiusang Mag-uuma sa Nueva Granada Nueva Granada Potable Water System Development Project: A Part of Buenavista Uplifting Groups for Water Access (BUGWAC) Brgy Nueva Granada, Buenavista, Bohol 7 mos 87 HH (622 individuals
639,041.56
29,700
75,850
533,491.56
-
-
12
Participatory Research, Organization of Communities & Education towards Struggle for Self-reliance - Bohol Upgrading of Level I Water System Katarungan, Ubay, Bohol 10 mos 186 HHs (1,055 individuals)
462,934
42,000
117,730
303,204
-
-
13
Nagkahiusang Inahan sa Hinlayagan Ilaya (NIHI) Level II Piped-Water System Development in Puroks 1 and 2, Hinlayagan Ilaya, Trinidad, Bohol Brgy. Hinlayagan Ilaya, Trinidad, Bohol 6 mos 48 HH (242 individuals
297,025
27,200
75,850
193,975
-
-
14
Alumar Women’s Organization Upgrading and Expansion of Alumar Water Level I System Alumar, Getafe, Bohol 1 year 148 Households
492,214
6,500
82,950
402,764
-
-
15
Kapunongan Alang sa Malambuong Katawhan Installation of Capayas   Level II Water System Brgy Capayas, San Miguel, Bohol 1 year 55 Households (Farmers
693,119
6,500
36,000
650,619
-
-
16
Campao Occidental Fishermens’ Association Upgrading and expansion of campao occidental Level II water system Getafe, Bohol 1 year 75 Households
894,643
6,500
52,500
835,643
-
-
17
Kagawasan Multi-Purpose Cooperative Installation of Kagawasan Level II Water System Kagawasan, San Miguel, Bohol 1 year 168 HHs
1,104,900
6,500
75,750
1,022,650
 
-
-
18
Panaghiusang Mag-uuma sa Cabangahan Installation of Cabangahan Level II   Water System Brgy Cabangahan, San Miguel, Bohol 1 year 140 Households (125 HH are farmers)
1,617,474
6,500
75,750
1,535,224
-
-
19
Villa Anunciado Samahang Nayon, Inc. Villa Anunciado Potable Level II Water System Brgy Villa Anunciado, Danao, Bohol 1 year 35 Households ( 104 individuals)
453,694.50
61,100
114,750
277,844.50
-
-
20
Ramon Aboitiz Foundation Inc. Expansion of the MORWASA Water System in Barangay Molobolo, Tuburan, Cebu Barangay Molobolo, Tuburan, Cebu 6 mos 1017HH (estimated 5085 individuals)
1,193,113.52
-
-
1,193,113.52
-
-
21
Aras-asan-Unidad Rural Water and Sanitation Association Rehabilitation and Construction of Potable Water System Level III Barangay Aras-asan, Cagwait, Surigao Del Sur 11 mos 137 micro- entrepreneurs; 668 multi-sectoral HHs
1,074,028
155,000
62,200
334,508
-
522,320
22
Kalusugan Alang sa Bayan, Inc. (KAABAY, Inc.) Magimon Water Spring Development Sitio Magimon, Gupitan, Kapalong, Davao del Norte 1 year 369 farmers   (68 HHs)
653,289
-
119,815
533,474
-
-
        TOTAL
20,332,413
949,500
1,471,745
17,388,848
-
522,320

[back to top]

Approved Projects by the Program Committee during its meeting on 23 November 2005

 
Proponent
Project Title
Project site(s)
Project Duration
Beneficiaries
Amount Approved
Total
Ins Support Grant
Client Devt Grant
Direct Project Cost
Restricted Grant
Grant
Loan
1 Oriental Mindoro NGO/PO Network Formation of the PAC Baco, Bulalacao, Roxas, San Teodoro, Pola, Socorro & Gloria; Oriental Mindoro 1 year 500 rural and urban HHs
1,973,900
734,900
120,000
750,000
369,000
0
2 Marinduque Diocesan Devt Coop Establishment of PAC in Marinduque Marinduque 1 year 5251 farmers, 3931 landless rural workers, 4156 fishers, 1872 wage-earners, 2070 micro entrepreneurs, 2567 HHs
1,160,110
534,910
44,000
258,700
322,500
0
3 Old Sta. Mesa Savings and Credit Coop Capability Building for OSMCC Manila City 6 mos 3660 wage-earners/ micro-entrepreneurs
400,000
0
300,000
100,000
0
0
4 Reconciliation Center - CCF Reconciliation Center Livelihood Project Cotabato City; Sultan Kudarat, Maguindanao; Datu Odin Sinsuat, Maguindanao 3 years 400 micro-entrepreneurs (380 female, 20 male)
1,150,000
50,000
100,000
0
1,000,000
0
5 Pusuac Multi-Purpose Cooperative Organic Fertilizer Production Training Diffun, Quirino 6 mos coop members
350,000
0
350,000
0
0
0
6 Hiyas Unlad Parent's Association, Inc. Strengtheing HUPAI's Micro Credit and Savings Project San Lusi and Taal, Batangas 3 years 160 individuals  987,000
130,000
57,000
0
800,000
0
7 Peoples Economic Advancement for Community Empowerment Foundation, Inc Expanded Savings and Credit for Community Devt Project 9 barangays of Bunawan District, Davao City 3 years 650 Urban Poor (Micro-Entrepreneurs)
1,700,000
180,000
20,000
0
1,500,000
0
8 St. Vincent Ferrer Parish Multi-Purpose Cooperative Inc Coco Methyl Ester (CME) Production Anahao, Odiongan, Romblon 3 years 600 farmers, 10 wage-earners
2,070,000
320,000
0
0
1,750,000
0
9 Zero Waste Recycling Movement of the Philippines Foundation, Inc. Deparo Integrated Solid Waste Management Project (DISWMP) Barangay Deparo, North Caloocan, Caloocan 6 mos 1000 Households in 5 Subdivisions  330,400
60,000
58,000
212,400
0
0
          TOTAL
10,121,410
2,009,810
1,049,000
1,321,100
5,741,500
-

Approved Projects by the Board of Trustees during its meeting on 24 November 2005.

  Proponent Project Title Project site(s) Project Duration Beneficiaries Amount Approved
Total
Ins Support Grant Client Devt Grant Direct Project Cost Credit Line
Grant Loan
1 Provincial Alliance of NGOs and POs for Development The Sorsogon Partnership and Access Center (Phase I) Pillar, Castilla, Magallanes, Bulan, Juban and Matnog, Sorsogon 1 year 1,500 farmers; 730 fisherfolk, 570 women micro- entrepreneurs         3,271,300 622,300 367,000 1,782,000 500,000 0
2 Kadtabanga Foundation for Peace and Development Advocates, Inc. Margues-Taviran Water Spring Development Barangay Margues and Taviran, Datu Odin Sinsuat, Maguindanao 1 year 654 HHs (3,270 individuals)    4,408,655.25 32,000 150,000 4,226,655.25 0 0
3 Coalition of Social Development Organizations in South Cotabato (CSDO) in partnership with the Provincial and Municipal Government Potable Water System Delivery in South Cotabato: "A Provincial Access Center and Local Government Unit Partnership" Phase II 16 barangays in South Cotabato 2 years 17,420 individuals or 3,484 HHs  26,189,594.78 2,182,466.23 2,182,466.23 21,824,662.33 0 0
4 MASS-SPECC Cooperative Development Center Synergizing for Poverty Reduction Action in Mindanao (SPREAD): MASS-SPECC Mindanao Coops Access Center 60% in PEF priority areas; 40% in non-priority areas in Mindanao 1 year 8,000 coop members in 20 coops       23,052,000 652,000 2,400,000 0 0 20,000,000
          TOTAL 56,921,550 3,488,766 5,099,466 27,833,318 500,000 20,000,000